NOT included in Schedule of Works - December 2013
or s.20 Notice dated 22 June 2014
The Schedule of Works - 7 February 2014
Management & Lessees NOT
requiring Solar Panels
(Management ) & Lessees NOT requiring Mirrors - Management in favour at some time
Still under consideration but requires 100% agreement of ALL nine Lessees - see 2005…?
Contractor/Supplier TBA
Management NOT recommending a Pro-floor clean due to cost - and TO PROVE A POINT compare WADE QUOTE
Contractor TBA
Professional Tender Specifications
Management are obliged to follow Head Lease requirements which is to paint & decorate, as well as repair and maintain the Communal areas of Mitre House.
Lessees cannot be required to pay for improvements nor cosmetic additions unless ALL Lessees agree to the additional expenditure over and above the minimum works required to be done.
If Management proceeded with expenditure over and above the minimum outlay required, those Lessees that do not wish to spend more than is minimally required can apply to the LVT for retribution and full reimbursement.
In February 2005 a Communal Sky Dish was proposed and a Section 20 Notice was raised, but one Lessee objected to the expenditure and the project was shelved.
As such, Management's Internals' budget of £25,000 incl. VAT adequately covers all that is required to paint & decorate, and repair and maintain the Communal areas and will not include any improvements or cosmetic items if they cannot be accomplished within the £25,000 budget.
Contractor/Supplier TBA
Contractor TBA
Contractor TBA - but only minimum required being Main Front Door furniture - NOT Lessees
Contractor TBA
Lessees' Analysis is NOT accurate and does NOT incl. VAT
Management NOT recommending a single Contractor
Must ONLY be viewed on a decent size screen - not a mickey mouse mobile...!
Management have sourced many quotes from many independent contractors as opposed to one main contractor as Management knows that this is the more economic way forward when budgets are of prime importance.
It is perfectly normal, legal and acceptable that ALL single main contractors farm work out to sub-contractors and most normally load the sub-contractors quotes by anything from 10% - %40 as indeed the example below amply evidences.
Type your paragraph here.
Type your paragraph here.
Contractor TBA
Contractor TBA
Contractor & Works TBA
WADE QUOTE (03/7/12 & 23/1/13) is THE Preferred contractor by Lessees for ALL Works and TOTALS a whopping £60,000 - £65,000 incl. VAT - Earlier Quotes (Stopps) was also considered too expensive by KFH (Stopps became WADE Design)
We rest our case.
£25,000 is the common sense budget.
Observations made and noted
(Management) & Lessees NOT in favour of Carpets - Management in favour at some time
All or some Quotes can now be considered somewhat out of time and might need re-quoting for better accuracy
Contractor TBA
Management are NOT recommending a
total Lift Refurb due to cost
NOT included in Schedule of Works - December 2013
or s.20 Notice dated 22 June 2014
Must ONLY be viewed on a decent size screen - not a mickey mouse mobile...!
NOT included in Schedule of Works - December 2013
or s.20 Notice dated 22 June 2014
Observations made and noted
Due to (some) Lessee requests
Due To (Some) Lessee requests
ALL included in Schedule of Works - December 2013
or s.20 Notice dated 22 June 2014